SSS #360: August 26 Recap - Business

Newsletter

Livin' La Vida Luna y Luca

First Day
First Day

First day of school superhero vibes

August 26 Recap - Business

To see my personal update for August, check out last week's email.

Step Count
Step Count

Solid showing in August. 109% of the monthly goal, which kept me steady at 104% of the yearly goal.

Project Girard

Project Girard
Project Girard

Project Bennington

Project Bennington
Project Bennington
  • 👐🏽 All done! Closing scheduled for 9/8.

Project Lorraine

Project Lorraine
Project Lorraine
  • So close to the finish line

Project Brightwood

Project Brightwood
Project Brightwood
  • Framing complete - windows are in, roof is on
  • Roughs almost complete
  • Interviewing agents

Project Lum

Project Lum
Project Lum
  • Looking like shovels in the ground by the end of September 🤞🏽

Project Townsend II

Project Townsend Part-Deux
Project Townsend Part-Deux
  • Framing Complete
  • Agent selected. Listing should go live in the next week or two

Project Hobart

  • Foundations complete
  • Framing starts next week

Project Kice II

Kice II
Kice II
  • Had a small environmental issue here that delayed demo-day a bit
  • Should have a hole in the ground by the end of September

Project Mackenzie

Project Mackenzie
Project Mackenzie
  • Foundation Complete (Slab poured)
  • Framing Complete (windows in, roof on, house wrapped)
  • Roughs to be complete by the end of September

Project Roosevelt

Project Roosevelt
Project Roosevelt
  • Purchase closing on September 21st
  • Plans are complete and ready to submit

With Girard off our books and Bennington + Lorraine rolling off in the next few weeks, it started to look like winter was coming.

Thankfully, we capitalized on August. While most people were away or simply took their foot off the gas, we put 3 new deals under contract. 😤

More on those soon.

Til then...✌🏽&❤️