
Nothing like 18" of snow, 2 days off school, and a delayed opening to make you wish you were still in Puerto Rico.
Feb '26 Recap
Let's start with a few personal things:
- The Group Chat met up IRL. 5 families. 18 people. 8 children 6 years old and under took Puerto Rico by storm. We're already planning next year's trip. If you told me 20 years ago I'd still be close friends with the guys I pledged with, I'd say... Obviously. 😄
- Despite the heavy snow, there were a handful of nice days this month. It felt great to go for walks outside.

- Speaking of walks - I just got by in Feb. Still ~650 steps/day above target, but not quite as good as Jan. I'm especially proud of my step count in Puerto Rico. I hit the gym every morning to run 5K, and the rest took care of itself.
- I'm impatiently waiting to buy an Amazfit Helio Strap (currently out of stock). I'm getting so sick and tired of carrying my phone everywhere to track steps.
Now Let's Get Down to Business...
Project Willow

- We're improving the price by $107K tomorrow
- A solid comp printed at $1.8M this past Friday
- Traffic remains steady. Sub-6% Mortgage Rates, March Market, & a 5%+ price reduction should do the trick.
Project Kice

- We accepted an offer and are in Attorney Review
- Estimated completion date is 4/30/26
Project Townsend

- We took Townsend OFF the market.
- We'll go back on after completion (3/31/26) at a higher price
Project Girard

- Foundation is complete, and Framing is in process
- House should be roofed and wrapped by the end of March
Project Bennington

- The house was torn down, and the lot was excavated
- We poured footings before the snowstorm
- Foundation walls to be installed this week
Project Lorraine

- Started the rendering package
- Luna and I watched them excavate for like 10 minutes earlier this week
- 15 trucks of dirt removed
- Foundation to be complete by the end of March
Project Brightwood

- Thought the house wb down by now, but it's still standing... yeah, yeah, yeah.
- Waiting for the gas line to get cut and capped. They said 4-8 weeks, it's been 6.
Project Lum

- Still waiting for the town to tell us our hearing date for our side-yard setback variance hearing.
NEW: Project Hobart 👀
Will share more about this one in ~2 weeks.
✌🏽